Brookfield Foundry Landowner Pty Ltd is undertaking a significant development of 405 Bourke Street, Melbourne. Brookfield Foundry Landowner Pty Ltd (The Principal) has engaged Multiplex Constructions Pty Ltd (MPX) as the head contractor under a fixed lump sum Design & Construct contract.

405 Bourke Street, Melbourne is a high profile, 38 level, Class A commercial development in the centre of Melbourne's CBD, totalling approximately 66,970 square metres (“sqm”) including: 63,120 sqm office NLA 3,280 sqm retail NLA 570 sqm End of Trip (“EOT”) facilities, 177 car bays and 40 motorcycle bays.

In line with the Australian Jobs Act 2013, Multiplex is committed to ensuring that information about opportunities to bid for work on the 405 Bourke St project is provided by all levels of the project’s supply chain – from procurement entities to lower tier suppliers.

Notification of Opportunities to supply goods and services
The below schedule provides a indicative list of goods and services to be procured for the project with an anticipated value ≥$1,000,000. Note, these proposed works are design to Australian Building Codes and Standards.

Expected opportunities 
 Goods
Blockwork
 Metalwork
 Carpentry
 Joinery
 Metal Deck Roofing
 Cladding and Louvres
 Suspended Ceilings and Plasterboard
 Toilet Partitions
Internal Glazing
Blinds
Carpet and Vinyl
Stone and Ceramic Tiling
Paint
Signage
Building Maintenance Unit
Access Floors


The information provided in the table above is based on an initial assessment by the Contractor, giving our best estimate while detailed design for the proposed works is still underway. This shall be rationalised to include only trade package opportunities of anticipated value ≥$1,000,000.00

Note: RFQ’s for these trades shall be sent via Aconex (www.aconex.com) to shortlisted entities only.

To express your interest in the works, please complete a Pre-Qualification Questionnaire (PQQ) and return it to the project procurement officer, Mr. Guan Tay, for consideration. The relevant email address is 405bourkestreet@multiplex.global. Note, expressions of interest not accompanied by a completed PQQ may be deemed non-conforming and prohibited from further consideration in the shortlisting process.

Procurement & Project Programme

Procurement:

  • EOI / PQQ program / process’ – June 1 to June 30, 2018
  • Shortlisted entities identified by July 31 – The Contractor’s commercial process
  • Shortlisted entities notified by 7th Aug, with anticipated programme for RFQ’s distribution and required submission dates The Contractor’s commercial process
  • Unsuccessful entities notified by 7th Aug, information provided on contact details and procedure for attaining feedback – The Contractor’s commercial process
  • RFQ/market engagement to form Stage 2 Final Offer, anticipated to commence between July 2018 and September 2019
    The Contractor’s normal commercial review process shall apply to the assessment of all received bids form shortlisted entities.

Project Programme:

Indicative Project Timeline

Activity Duration
Podium Structure Aug 18 – July 19
Office Tower Structure Mar 19 – Jul 20
Facade May 19 – Sep 20
Lifts & Plant Jun 19 – Nov 20
399 Bourke St upgrade Sep 18 – Jul 19
Low Rise Tower Office Floors May 19 – Oct 20
Mid Rise Tower Office Floors Oct 19 – Nov 20
High Rise Tower Office Floors Mar 20 – Feb 21

 